STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: January 10, 2024
COUNCIL DISTRICT(S): All
DEPARTMENT: Water Utilities Department
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT
Title
Authorize a thirty-six-month construction services contract for pavement repairs at various locations throughout the city supporting water and wastewater operations of the Dallas Water Utilities Department - Omega Contracting, LLC, lowest responsible bidder of two - Not to exceed $34,717,342.80 - Financing: Water Construction Fund ($26,730,917.80) and Wastewater Construction Fund ($7,986,425.00) (subject to annual appropriations)
Body
BACKGROUND
This action will authorize pavement repairs at various locations throughout the city supporting water and wastewater operations for the Dallas Water Utilities Department. The contract will be utilized for pavement and surface repairs to streets, alleys, sidewalks, medians, parkways, parking lots, and other areas resulting from water and wastewater main repairs. Approval of this contract will allow for the expeditious restoration of pavement and other surfaces following the completion of water and wastewater infrastructure repairs.
The existing contract for pavement repairs is expected to be exhausted of funds in February 2024.
The following chart illustrates Omega Contracting, LLC's contractual activities with the City of Dallas for the past three years:
PBW DWU PKR TRN
Projects Completed|9 99 9 10|Active Projects|9 99 9 10|Change Orders|9 9 9 9 10|Projects Requiring Liquidated Damages|9 9 9 9 10|Projects Completed by Bonding Company|9 9 9 9 10|
ESTIMATED SCHEDULE OF PROJECT
Begin Construction February 2024
Complete Construction February 2027
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
This item has no prior action.
FISCAL INFORMATION
Fund
FY 2024
FY 2025
Future Years
Water Construction Fund
$ 8,910,305.93
$8,910,305.93
$8,910,305.94
Wa...