STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: March 27, 2024
COUNCIL DISTRICT(S): 4
DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT
Title
Authorize Supplemental Agreement No. 3 to the professional services contract with Halff Associates, Inc., to provide additional engineering and archeological survey services needed for 10th Street from Interstate Highway 35 to Clarendon Drive to mitigate potential risk to the cemetery at 100 North Moore Street - Not to exceed $76,647.45, from $503,665.40 to $580,312.85 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Body
BACKGROUND
On June 26, 2019, the City Council authorized a professional services contract with Halff Associates, Inc. for the engineering design of a local street reconstruction project on 10th Street from Interstate Highway 35 to Clarendon Drive by Resolution No. 19-0983.
To minimize the construction impact of the 10th Street Project on the cemetery at 100 North Moore Street, the Landmark Commission requested an archeological survey of the slopes along the cemetery within the limits of the 10th Street Project. The archeological survey was submitted to the Texas Historical Commissions (THC) for review. The THC review comments requested for additional archeological survey and On-the-Ground survey of identified objects and Texas Antiquities Permit for construction and archeological monitoring during construction. Consequently, it is necessary to add the required archeological survey and construction monitoring services to the contract.
This action will authorize Supplemental Agreement No. 3 to the professional services contract with Halff Associates, Inc. to provide additional engineering and archeological survey services needed for 10th Street from Interstate Highway 35 to Clarendon Drive to mitigate potential risk to the cemetery at 100 North Moore Street.
Halff Associates, Inc. is a Richardson-based corporation and is a registered vendor with the City of Dallas.
If this action is delayed or deferred, the construction schedule could be delayed. Field conditions may also change, which will require modifications to the engineering design plans, requiring additional funding and time to address.
ESTIMATED SCHEDULE OF PROJECT
Began Design August 2019
Complete Design May 2024
Begin Construction August 2024
Complete Construction December 2025
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On June 26, 2019, the City Council authorized a professional engineering services contract with Halff Associates, Inc., for the engineering design of a local street reconstruction project on 10th Street from Interstate Highway 35 to Clarendon Drive, by Resolution No. 19-0983.
On September 28, 2022 the City Council authorized Supplemental Agreement No. 1 to the professional services contract with Halff Associates, Inc., to provide additional engineering design services and necessary design modifications of 10th Street from lnterstate Highway 35 to Clarendon Drive to avoid impact to the cemetery at 100 North Moore Street, by Resolution No. 22-1455.
FISCAL INFORMATION
Fund |
FY 2024 |
FY 2025 |
Future Years |
Street and Transportation (A) Fund |
$76,647.45 |
$0.00 |
$0.00 |
Engineering Services Contract $290,165.40
Supplemental Agreement No. 1 $134,500.00
Supplemental Agreement No. 2 $ 79,000.00
Supplemental Agreement No. 3 (this action) $ 76,647.45
Total amount not to exceed $580,312.85
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$76,647.45 |
Architecture & Engineering |
25.66%* |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
2.89% |
2.89% |
$2,215.00 |
• *This item reflects previous Business Inclusion and Development Policy M/WBE goal |
• This contract does not meet the M/WBE goal, |
• Supplemental Agreement No 3 - 24.01% Overall MWBE participation |
• Halff Associates, Inc. - Local; Workforce - 17.00% Local |
OWNER
Halff Associates, Inc.
Todd Woodson, P.E., Vice President
MAP
Attached