Dallas Logo
File #: 24-991    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 3/14/2024 In control: Park & Recreation Department
On agenda: 4/10/2024 Final action:
Title: Authorize a construction services contract for the construction of the Coombs Creek Extension Trail Improvements from Davis Street to Moss Park Project located at the 500 Block of North Plymouth Road - Northstar Construction, LLC, lowest responsible bidder of four - Not to exceed $567,750.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds)
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: April 10, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the construction of the Coombs Creek Extension Trail Improvements from Davis Street to Moss Park Project located at the 500 Block of North Plymouth Road - Northstar Construction, LLC, lowest responsible bidder of four - Not to exceed $567,750.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds)

Body
BACKGROUND

On November 3, 2023, four bids were received for the construction of the Coombs Creek Extension Trail Improvements Project. This action will authorize a construction services contract with Northstar Construction, LLC, lowest responsible bidder of four, for the construction of the Base Bid, in the amount of $567,750.00.

The scope of work for the Coombs Creek Extension Trail Improvements from Davis Street to Moss Park includes construction of the Coombs Creek Extension Trail consisting of 10-foot-wide concrete trail along Plymouth Road from Davis Street to Moss Park, including accessible ramps, pavement striping, pedestrian crossing improvements, drainage improvements, park trail head improvements and other associated improvements. Funding for this project was included in the 2017 Bond Program.

The following chart illustrates Northstar Construction, LLC's contractual activities with the City of Dallas for the past three years.

PBW DWU PKR TRN

Projects Completed|999910|Change Orders|999910|Projects Requiring Liquidated Damages|999910|Projects Completed by Bonding Company|999910|
ESTIMATED SCHEDULE OF PROJECT

Began Construction May 2024
Complete Construction November 2024

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On March 21, 2024, the Park and Recreation Board authorized a construct...