STRATEGIC PRIORITY: Sustainable
AGENDA DATE: May 14, 2025
COUNCIL DISTRICT(S): 6
DEPARTMENT: Department of Aviation
EXECUTIVE: Dev Rastogi
______________________________________________________________________
SUBJECT
Title
Authorize Supplemental Agreement No. 1 to the architectural services contract with McAfee3 Architecture, inc. to amend the scope of work to include construction administration phase services for the redesign and co-location of the Airport Operation Center/Airport Emergency Operation Center at Dallas Love Field - Not to exceed $172,500.00, from $250,000.00 to $422,500.00 - Financing: Aviation Fund
Body
BACKGROUND
The Airport Operation Center (AOC) is an integral part of daily airport operations, which requires a standard of functional requirements for 24/7 operational support during normal conditions, irregular operation, and emergency situations. The Airport Emergency Operation Center (AEOC) is an essential component of emergency response and recovery where key officials can collect, communicate, and coordinate information and resources. The current layout, equipment, and resources are not sufficient in enabling the AOC/AEOC core functions.
The project intent for co-location of these two critical functions is the ability to collect, analyze, and share information between AOC/AEOC quickly and face-to-face during emergency management, and to redesign each center allowing for optimal operations in support of daily and emergent events. McAfee3 Architecture, inc. is analyzing the AOC and designing a space to facilitate the current industry needs in similar facilities and its technological needs.
This action will authorize Supplemental Agreement No. 1 to the architectural services contract with McAfee3 Architecture, inc., to amend the scope of work to include construction administration phase services for the redesign and co-location of the AOC/AEOC at Dallas Love Field in an amount not to exceed $172,500.00, from $250,000.00 to $422,500.00.
ESTIMATED SCHEDULE OF PROJECT
Began Design October 2023
Completed Design December 2024
Begin Construction July 2025
Complete Construction July 2026
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On June 28, 2023, the City Council authorized an architectural services contract with McAfee3 Architecture, Inc., to provide design services and bid phase services for the Airport Operation Center/Airport Emergency Operation Center at Dallas Love Field by Resolution No. 23-0874.
FISCAL INFORMATION
Fund |
FY 2025 |
FY 2026 |
Future Years |
Aviation Fund |
$172,500.00 |
$0.00 |
$0.00 |
Original Contract $250,000.00
Supplemental Agreement No. 1 (this action) $172,500.00
Total $422,500.00
M/WBE INFORMATION
In accordance with the City’s Business Inclusion and Development Policy adopted on September 23, 2020, by Resolution No. 20-1430, as amended, the M/WBE participation on this contract is as follows:
Contract Amount |
Procurement Category |
M/WBE Goal |
$172,000.00 |
Architecture & Engineering |
34.00% |
M/WBE Subcontracting % |
M/WBE Overall % |
M/WBE Overall Participation $ |
19.72% |
76.90% |
$132,660.00 |
• This contract does not meet the M/WBE goal, but complies with good faith efforts. |
• McAfee3 Architecture, Inc. - Local; Workforce - 47.83% Local |
OWNER EXECUTIVE
McAfee3 Architecture, inc.
Charyl F. McAfee-Duncan, FAIA, Principal
MAP
Attached