File #: 22-1637    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/20/2022 In control: Department of Transportation
On agenda: 9/28/2022 Final action:
Title: Authorize a Multiple Use Agreement with the Texas Department of Transportation for the use of right-of-way at the Routh Street/Woodall Rodgers Intersection as part of the Routh Street Gateway Sidewalk Improvement Project (AD465121) - Financing: This action has no cost consideration to the City (see Fiscal Information)
Indexes: 14
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: September 28, 2022
COUNCIL DISTRICT(S): 14
DEPARTMENT: Department of Transportation
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

title
Authorize a Multiple Use Agreement with the Texas Department of Transportation for the use of right-of-way at the Routh Street/Woodall Rodgers Intersection as part of the Routh Street Gateway Sidewalk Improvement Project (AD465121) - Financing: This action has no cost consideration to the City (see Fiscal Information)

body
BACKGROUND

On August 26, 2020, City Council authorized the Development Participation Contract with the Dallas Arts District Foundation for donation of design plans and specifications for the construction of the Routh Street Gateway Sidewalk Improvement Project, by Resolution No. 20-1228. The Routh Street Gateway Sidewalk Improvement Project (AD465121) was approved as part of the 2017 Bond Program. This partnership will expand and update wayfinding, signage, public art, and enhance pedestrian connections in all directions along Routh Street Gateway. The Dallas Arts District Foundation agreed to provide all necessary engineering and design services associated with this project at their own cost and expense and donate all design documents and plans for the City to facilitate the construction.

In order to proceed with certain procurements and the construction associated with this project, it is necessary to execute a Multiple Use Agreement (MUA) with the Texas Department of Transportation. This MUA will allow the use of certain right-of-way at the Routh Street/Woodall Rodgers Intersection.

Future Operations and Maintenance costs associated with the improvements related to the civil work being done will be the responsibility of the City of Dallas.








ESTIMATED SCHEDULE OF PROJECT

Began Design May 2019
Completed Design April 2022
Begin Construction November 2022
Complete Constr...