Dallas Logo
File #: 23-1764    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 6/26/2023 In control: Park & Recreation Department
On agenda: 8/9/2023 Final action:
Title: Authorize a construction services contract for the Anderson Bonner Park New Playground Project located at 12000 Park Central Drive - Alpha Omega Professional Services Group LLC, lowest responsible bidder of two - Not to exceed $144,127.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds)
Indexes: 11
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Quality of Life, Arts & Culture
AGENDA DATE: August 9, 2023
COUNCIL DISTRICT(S): 11
DEPARTMENT: Park & Recreation Department
EXECUTIVE: John D. Jenkins
______________________________________________________________________
SUBJECT

Title
Authorize a construction services contract for the Anderson Bonner Park New Playground Project located at 12000 Park Central Drive - Alpha Omega Professional Services Group LLC, lowest responsible bidder of two - Not to exceed $144,127.00 - Financing: Park and Recreation Facilities (B) Fund (2017 General Obligation Bond Funds)

Body
BACKGROUND

On March 15, 2023 and March 22, 2023, the City of Dallas advertised for bids for the Anderson Bonner Park New Playground Project located at 12000 Park Central Drive. In response to the advertisement, the Office of Procurement Services received bids from two firms on April 7, 2023.

Alpha Omega Professional Services Group LLC was selected as the lowest responsible bidder for the Base Bid, in an amount not to exceed $144,127.00.

The scope of work for the Anderson Bonner Park New Playground Project includes construction and installation of new playground equipment, concrete flat work, benches, erosion control, tree protection, concrete walkway with connection and miscellaneous drainage.

The following chart illustrates Alpha Omega Professional Services Group LLC's contractual activities with the City of Dallas for the past three years.

PBW DWU PKR TRN

Projects Completed|999910|Active Projects|99999|
Change Orders|999 910|Projects Requiring Liquidated Damages|99999|
Projects Completed by Bonding Company|9999| 0

ESTIMATED SCHEDULE OF PROJECT

Began Design April 2022
Design Completed January 2023
Begin Construction August 2023
Complete Construction December 2023

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On, June 28, 2023, the Park and Recreation Board authorized a construction services contract for the Anderson Bonner Park New Pl...

Click here for full text