Dallas Logo
File #: 24-725    Version: 1 Name:
Type: CONSENT AGENDA Status: Agenda Ready
File created: 2/22/2024 In control: Department of Public Works
On agenda: 4/24/2024 Final action:
Title: Authorize a professional services contract with Burgess & Niple, Inc. to provide engineering design services for West Davis Street from North Hampton Road to North Clinton Avenue - Not to exceed $1,388,620.00 - Financing: 2023 Certificate of Obligation Fund ($1,309,060.00), Water Capital Improvement G Fund ($56,487.60), and Wastewater Capital Improvement F Fund ($23,072.40)
Indexes: 1
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: April 24, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize a professional services contract with Burgess & Niple, Inc. to provide engineering design services for West Davis Street from North Hampton Road to North Clinton Avenue - Not to exceed $1,388,620.00 - Financing: 2023 Certificate of Obligation Fund ($1,309,060.00), Water Capital Improvement G Fund ($56,487.60), and Wastewater Capital Improvement F Fund ($23,072.40)

Body
BACKGROUND

A Request for Qualifications (CIZ23-PBW-3013) was issued on April 26, 2023, for the Street and Transportation Design Services for Special Projects. Burgess & Niple, Inc. was selected following a qualifications-based selection process by the City of Dallas procurement guidelines.

This action will authorize a professional services contract with Burgess & Niple, Inc. for the engineering design of West Davis Street from North Hampton Road to North Clinton Avenue. The scope includes evaluating typical section alternatives, paving and drainage design, dedicated bike lanes, sidewalks and drive approaches, streetscape/landscape, curbs and gutters, storm drainage, traffic signals, pedestrian/streetlights, water, and wastewater mains replacement.

At this point, some tasks like traffic control plans and subsurface utility engineering have been deferred to a future supplemental agreement.

ESTIMATED SCHEDULE OF PROJECT

Begin Design June 2024
Complete Design November 2025

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.


FISCAL INFORMATION

Fund
FY 2024
FY 2025
Future Years
2023 Certificate of Obligation Fund
$1,309,060.00
$0.00
$0.00
Water Capital Improvement G Fund
$ 56,487.60
$0.00
$0.00
Wastewater Capital Improvement F Fund
$ 23,072.40
$0.00
$0.00
Total
$1,388,620.00...