Title: Authorize an increase in the construction services contract with HD Way Concrete Service, LLC for the additional water adjustments and wastewater main improvements needed on Street Reconstruction Group 17-4009 - Not to exceed $163,375.00, from $2,090,214.00 to $2,253,589.00 - Financing: Wastewater Capital Improvement F Fund ($155,875.00) and Water Construction Fund ($7,500.00)
Indexes: 4
Attachments: 1. Maps, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: April 24, 2024
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

Title
Authorize an increase in the construction services contract with HD Way Concrete Service, LLC for the additional water adjustments and wastewater main improvements needed on Street Reconstruction Group 17-4009 - Not to exceed $163,375.00, from $2,090,214.00 to $2,253,589.00 - Financing: Wastewater Capital Improvement F Fund ($155,875.00) and Water Construction Fund ($7,500.00)

Body
BACKGROUND

On June 14, 2023, the City Council authorized the construction services contract with HD Way Concrete Service, LLC, for the construction of Street Reconstruction Group 17-4009, by Resolution No. 23-0781.

During construction, it was discovered that to complete the proposed storm drainage construction on Montague Avenue, additional wastewater improvements are needed to clear the conflicting wastewater lateral encountered. It is also necessary to investigate the existing water main on Vanette Lane to determine the extent of its encasement in 5-feet of flowable fill and the possible conflict with the proposed water main. This will require adding the additional water adjustments and wastewater main improvements needed to the contract.

This action will authorize Change Order No. 1 to the construction services contract with HD Way Concrete Service, LLC for the additional water adjustments and wastewater main improvements needed on Street Reconstruction Group 17-4009.

HD Way Concrete Service, LLC is located in Grand Prairie, Texas, and is a registered vendor with the City of Dallas.

ESTIMATED SCHEDULE OF PROJECT

Began Construction October 2023
Complete Construction December 2024

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On June 14, 2023, the City Council authorized a construction services contrac...