Dallas Logo
File #: 20-390    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/19/2020 In control: Department of Public Works
On agenda: 9/23/2020 Final action: 9/23/2020
Title: Authorize Supplemental Agreement No. 2 to the professional services contract with DAL-TECH Engineering, Inc. for additional engineering design of paving, drainage, and water and wastewater main improvements for The Bottom Phase II Project - Spark Street from Hutchins Avenue to Levee; Cleaves Street from Hutchins Avenue to Levee; Hart Street from Canyon Avenue to Levee; and Connector #1 between Cleaves Street and Hart Street - Not to exceed $612,580.00, from $1,606,713.50 to $2,219,293.50 - Financing: Street and Transportation Improvements Fund (2003 General Obligation Bond Funds) ($413,700.00), Water Utilities Capital Improvement D Funds ($30,000.00), and Wastewater Utilities Capital Improvement E Funds ($168,880.00)
Indexes: 4
Attachments: 1. Map, 2. Resolution, 3. Staff Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 23, 2020
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 2 to the professional services contract with DAL-TECH Engineering, Inc. for additional engineering design of paving, drainage, and water and wastewater main improvements for The Bottom Phase II Project - Spark Street from Hutchins Avenue to Levee; Cleaves Street from Hutchins Avenue to Levee; Hart Street from Canyon Avenue to Levee; and Connector #1 between Cleaves Street and Hart Street - Not to exceed $612,580.00, from $1,606,713.50 to $2,219,293.50 - Financing: Street and Transportation Improvements Fund (2003 General Obligation Bond Funds) ($413,700.00), Water Utilities Capital Improvement D Funds ($30,000.00), and Wastewater Utilities Capital Improvement E Funds ($168,880.00)

Body
BACKGROUND

DAL-TECH Engineering, Inc. is a Dallas-based corporation, operating within the corporate city limits of Dallas, Texas.

On January 12, 2011, City Council authorized a professional services contract, No. 10-207E/208E with DAL-TECH Engineering, Inc. to provide engineering design services for the renewal of water and wastewater mains at 34 locations by Resolution No. 11-0187.

On August 24, 2016, City Council authorized Supplemental Agreement No. 1 to the professional services contract with DAL-TECH Engineering, Inc. for additional design services for paving, drainage, and water and wastewater main improvements in The Bottom Area by Resolution No. 16-1356.

On November 30, 2018, a request was received from the Department of Housing and Neighborhood Revitalization and the Planning and Urban Design Department to divide The Bottom Project into two phases for construction.



On May 22, 2019, City Council authorized the construction services contract with Mu...

Click here for full text