Dallas Logo
File #: 20-1336    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 7/14/2020 In control: Department of Public Works
On agenda: 9/23/2020 Final action: 9/23/2020
Title: Authorize a construction contract for the construction of Alley Reconstruction Group 12-2034 (list attached to the Agenda Information Sheet) - Vescorp Construction, LLC dba Chavez Concrete Cutting, lowest responsible bidder of eight - Not to exceed $1,784,620.00 - Financing: Street and Transportation Improvements Fund (2012 General Obligation Bond Funds)
Indexes: 12
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: September 23, 2020
COUNCIL DISTRICT(S): 12
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize a construction contract for the construction of Alley Reconstruction Group 12-2034 (list attached to the Agenda Information Sheet) - Vescorp Construction, LLC dba Chavez Concrete Cutting, lowest responsible bidder of eight - Not to exceed $1,784,620.00 - Financing: Street and Transportation Improvements Fund (2012 General Obligation Bond Funds)

Body
BACKGROUND

Vescorp Construction, LLC dba Chavez Concrete Cutting is a Balch Springs-based corporation, operating within the corporate city limits of Balch Springs, Texas. This action will authorize a construction contract with Vescorp Construction, LLC dba Chavez Concrete Cutting for the construction of six alley reconstruction projects as Alley Reconstruction Group 12-2034. The alley reconstruction projects will include replacing the existing deteriorating alleys with new reinforced concrete alley pavement, drive approaches, and storm drainage improvements.

Following are the locations and construction costs for each project:

Project Council District Amount

Country Brook Drive (4204 - 4328) 12 $410,395.00

Gray Wolf Trail (6203 - 6251) and
Bentwood Trail (6211 - 6247) 12 $160,175.00

Hilton Head Drive (5211 - 5315) and
River Hill Circle (4708 - 4724) 12 $211,110.00

Hilton Head Drive (5310 - 5420) and
Harbor Town Drive (5305 - 5323) 12 $212,600.00

Park Grove Lane (18627 - 18851) and
Kirkmeadow Lane (4007 - 4131) 12 $352,000.00

Tree Shadow Trail (5902 - 5942) and
Flintshire Court (5901 - 5923) 12 $438,340.00

The following chart illustrates Vescorp Construction, LLC dba Chavez Concrete Cutting's contractual activities with the City of Dallas for the past three years:

PBW DWU P...

Click here for full text