File #: 20-2506    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 12/17/2020 In control: Building Services Department
On agenda: 1/27/2021 Final action:
Title: Authorize Supplemental Agreement No. 3 to increase the professional services contract with Terracon Consultants, Inc. for engineering design plans and specifications for repairs and to provide construction administration services during the construction phase for structural repairs at Fire Station No. 30 located at 11381 Zodiac Lane - Not to exceed $124,000.00, from $49,325.00 to $173,325.00 - Financing: Capital Construction Fund
Indexes: 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: January 27, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Building Services Department
EXECUTIVE: Joey Zapata
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 3 to increase the professional services contract with Terracon Consultants, Inc. for engineering design plans and specifications for repairs and to provide construction administration services during the construction phase for structural repairs at Fire Station No. 30 located at 11381 Zodiac Lane - Not to exceed $124,000.00, from $49,325.00 to $173,325.00 - Financing: Capital Construction Fund

Body
BACKGROUND

In October 2019, cracks were observed in the brick walls and the foundation slab of the apparatus bay at Fire Station No. 30. The cracks widened and caused wall shifting, settlement and falling brick veneers. Terracon Consultants, Inc. was engaged on an emergency basis for a structural assessment. The conditions presented a safety risk to the occupants and the Building Services Department recommended the station be vacated in November 2019. On November 12, 2019, an emergency administrative action was ratified for Terracon Consultants, Inc. to provide a geotechnical engineering distress and structural integrity review of Fire Station No. 30 to determine the condition and the options available for corrective action.

In order for the engineering team to start their assessment, subsurface exploration, and testing, a safe environment had to be constructed. Terracon Consultants, Inc. developed a shoring plan to reinforce the wall, roof trusses, and the beams in the apparatus bay.

On September 18, 2020, Supplemental Agreement No. 1 was authorized for Terracon Consultants, Inc. to perform pile integrity testing and the final structural integrity review. Pile integrity testing was needed on the foundation under the north wall of the apparatus b...