Dallas Logo
File #: 21-236    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/2/2021 In control: Department of Public Works
On agenda: 4/14/2021 Final action:
Title: Authorize an increase to the construction services contract with DDM Construction Corporation to allow for additional removal of concrete pavement for Street Reconstruction Group 17-6001 (list attached to the Agenda Information Sheet) - Not to exceed $390,996.63, from $4,181,920.70 to $4,572,917.33 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)
Indexes: 2, 6
Attachments: 1. List, 2. Maps, 3. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: April 14, 2021
COUNCIL DISTRICT(S): 2, 6
DEPARTMENT: Department of Public Works
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize an increase to the construction services contract with DDM Construction Corporation to allow for additional removal of concrete pavement for Street Reconstruction Group 17-6001 (list attached to the Agenda Information Sheet) - Not to exceed $390,996.63, from $4,181,920.70 to $4,572,917.33 - Financing: Street and Transportation (A) Fund (2017 General Obligation Bond Fund)

Body
BACKGROUND

Due to unforeseen field conditions, the quantities of bid item 201- REMOVE CONCRETE PAVEMENT, DRIVE AND APRON will substantially exceed the original calculated amount. The construction documents do not show reinforced concrete pavement underneath the asphalt road since the bore logs that were provided by the geotechnical investigation do not illustrate any reinforced concrete underneath the roadway. The bid quantities were accounted for as unclassified street excavation for Street Reconstruction Group 17-6001.

This action will authorize payment for all additional concrete removals needed to complete the project.

Delays in processing the change order will lead to payment interruption to the contractor.

Following are the locations and costs for each project:

Street Reconstruction - Local Streets - Improvements

Project Council District Amount

Lenel Place (Partnership with District 2)
from Clover Lane to Wemdon Drive|99|$ 95,554.80
Wemdon Drive|99|$107,499.15

Lenel Place from Lively Lane
to Clover Lane|99|$ 97,598.25

Lenel Place from Wemdon Drive
to Mixon Drive|99|$ 90,344.43

DDM Construction Corporation is a registered vendor with the City and has an office in Addison, Texas.

ESTIMATED SCHEDULE OF PROJECT

Began Construction July 2020
Complete Construction October 2021

PRIOR ...

Click here for full text