Dallas Logo
File #: 21-755    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/16/2021 In control: Office of Bond and Construction Management
On agenda: 5/12/2021 Final action:
Title: Authorize Supplemental Agreement No. 4 to the design-build services contract with Harrison Walker & Harper, LLC. to provide construction services for the new Fire Station No. 46 replacement facility, located at 331 East Camp Wisdom Road - Not to exceed $187,914.00, from $6,073,065.60 to $6,260,979.60 - Financing: Public Safety (G) Fund (2017 General Obligation Bond Fund)
Indexes: 3
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: May 12, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Office of Bond and Construction Management
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 4 to the design-build services contract with Harrison Walker & Harper, LLC. to provide construction services for the new Fire Station No. 46 replacement facility, located at 331 East Camp Wisdom Road - Not to exceed $187,914.00, from $6,073,065.60 to $6,260,979.60 - Financing: Public Safety (G) Fund (2017 General Obligation Bond Fund)

Body
BACKGROUND

The replacement of Fire Station No. 46 facility was approved in the 2017 Bond Program by Dallas voters.

On April 10, 2019, Harrison Walker & Harper, LLC., was awarded the design-build services contract of the new Fire Station No. 46 replacement facility to be located at 331 East Camp Wisdom Road by Resolution No. 19-0499.

This action will authorize an increase to the design-build contract with Harrison Walker & Harper, LLC. for the installation of the radio alerting system for this replacement facility.

Deferral of this item would delay the project's completion date, which will negatively impact response times for Fire Station No. 46 service area. Fire Station No. 46 provides crucial fire and rescue services to the citizens of Dallas. The new facility is currently expected to open in July 2021.

ESTIMATED SCHEDULE OF PROJECT

Begin Design April 2019
Complete Design January 2020
Begin Construction January 2020
Complete Completion July 2021



PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On April 10, 2019, City Council authorized a design-build services contract with Harrison Walker & Harper, LLC. for design and pre-construction services, an early construction package, and architectural and engineering services for the design and construction of the Fire Station No. 46 replacem...

Click here for full text