File #: 21-1049    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 5/24/2021 In control: Department of Transportation
On agenda: 6/23/2021 Final action:
Title: Authorize payment to the Texas Department of Transportation for cost overruns related to the intersection and traffic signal improvements, including widening the bridge to add turn lanes, improving the approach, and replacing the traffic signal system at the intersection of Interstate Highway 20 and Bonnie View Road (CSJ 2374-03-074, CFDA No. 20.205) in the amount of $527,505.50 - Financing: General Fund ($427,505.50) and Street and Transportation Improvements Fund (2012 General Obligation Bond Funds) ($100,000.00)
Indexes: 8
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Mobility Solutions, Infrastructure, and Sustainability
AGENDA DATE: June 23, 2021
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Transportation
EXECUTIVE: Majed Al-Ghafry
______________________________________________________________________
SUBJECT

title
Authorize payment to the Texas Department of Transportation for cost overruns related to the intersection and traffic signal improvements, including widening the bridge to add turn lanes, improving the approach, and replacing the traffic signal system at the intersection of Interstate Highway 20 and Bonnie View Road (CSJ 2374-03-074, CFDA No. 20.205) in the amount of $527,505.50 - Financing: General Fund ($427,505.50) and Street and Transportation Improvements Fund (2012 General Obligation Bond Funds) ($100,000.00)

body
BACKGROUND

This project, initiated by the City of Dallas, is located at Bonnie View Road and Interstate Highway 20. It is an on-system project being constructed by the Texas Department of Transportation (TxDOT). It widens the bridge to add turn lanes, improves the approach, and replaces the traffic signal system.

On March 24, 2021, City Council authorized an Advance Funding Agreement (AFA) with TxDOT for this project by Resolution No. 21-0495. State and federal funding approved for this project totaled $2,718,645.00 and the engineer's cost estimate was $2,481,972.00. Although, this is a TxDOT project and because the City initiated the request for the project, the City had to agree to pay for cost overruns.

The project was let on May 6, 2021. Five bidders submitted their bids to TxDOT, with the low bidder being 33.8% over the engineer's cost estimate resulting in a cost overrun in the amount of $527,505.50. The bids were higher than the engineer's estimate primarily due to the increased cost of steel and the more complex nature of traffic control required during construction. With the overrun, the City's total contribution to the project is approximately 16% of...