Dallas Logo
File #: 22-963    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 4/13/2022 In control: Department of Aviation
On agenda: 5/25/2022 Final action:
Title: Authorize (1) an increase in the construction services contract with Flatiron Constructors, Inc. to provide additional construction services for the Reconstruction of Runway 13R-31L and Taxiway C Phase I Project at Dallas Love Field; and (2) an increase in appropriations in an amount not to exceed $4,994,038.70 in the 2021 AVI Commercial Paper Fund - Not to exceed $4,994,038.70, from $124,623,248.58 to $129,617,287.28 - Financing: 2021 AVI Commercial Paper Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: May 25, 2022
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

Title
Authorize (1) an increase in the construction services contract with Flatiron Constructors, Inc. to provide additional construction services for the Reconstruction of Runway 13R-31L and Taxiway C Phase I Project at Dallas Love Field; and (2) an increase in appropriations in an amount not to exceed $4,994,038.70 in the 2021 AVI Commercial Paper Fund - Not to exceed $4,994,038.70, from $124,623,248.58 to $129,617,287.28 - Financing: 2021 AVI Commercial Paper Fund

Body
BACKGROUND

The original project includes reconstruction of Runway 13R/31L, reconfiguration of taxiway connectors, and reconstruction of Taxiway C from Taxiway D to the 31L approach end (Phase I). The project will also include improvements to the existing drainage and storm water control system, replacement of airfield lighting, improvements to communications pathways and Aircraft Rescue and Firefighting roadway system and portion of the Vehicle Service Road.

Change Order No. 1 authorized funding to extend the runway closure duration by an additional 30 days to accommodate the additional scope added to the project to comply with the Federal Aviation Administration requirements. The change order also addressed changes in material quantities.

Change Order No. 2 authorized funding for construction changes due to additional work associated with storm drainage infrastructure, airfield lighting, concrete pavement section and pavement markings. Change Order No. 2 also adjusted the contract calendar days due to inclement weather experienced on the project.

This action will authorize Change Order No. 3 to the construction services contract for construction changes due to additional work associated with unforeseen work not reasonably within the s...