Title: Authorize Supplemental Agreement No. 2 to the professional services contract with HNTB Corporation to provide construction support services for the Runway 13R/31L Reconstruction Project at Dallas Love Field - Not to exceed $1,214,073.00 from $9,965,821.00 to $11,179,894.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 22, 2022
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Aviation
EXECUTIVE: Kimberly Bizor Tolbert
______________________________________________________________________
SUBJECT

Title
Authorize Supplemental Agreement No. 2 to the professional services contract with HNTB Corporation to provide construction support services for the Runway 13R/31L Reconstruction Project at Dallas Love Field - Not to exceed $1,214,073.00 from $9,965,821.00 to $11,179,894.00 - Financing: Aviation Passenger Facility Charge - Near Term Projects Fund

Body
BACKGROUND

On April 25, 2018, City Council authorized a professional services contract with HNTB Corporation for design, planning, engineering and construction document services for the Runway 13R/31L Reconstruction Project at Dallas Love Field.

The project includes the replacement of the existing pavement system, improvements to the existing drainage and storm water control system, replacement of airfield lighting improvements to communications pathways and Aircraft Rescue and Firefighting roadway system, and reconstruction portion of the Vehicle Service Road.

On May 27, 2020, City Council authorized Supplemental Agreement No.1 to the professional services contract with HNTB Corporation to provide full time on-site construction support services for the Runway 13R/31L Reconstruction Project at Dallas Love Field.

This action will authorize Supplemental Agreement No. 2 to the extend Resident Project Representative and professional services contract with HNTB Corporation. This will allow HNTB Corporation to continue to provide full time on-site construction support services for the Runway 13R/31L Reconstruction Project at Dallas Love Field.




ESTIMATED SCHEDULE OF PROJECT

Began Design April 2018
Completed Design January 2020
Began Construction March 2021
Complete Construction October 2022

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

On April 25, ...