Title: Authorize a construction contract for the Tornado-Damaged Signals Group 1 project consisting of re-construction of traffic signals located at Midway Road and Killion Drive, Preston Road (SH 289) and Preston Royal Center (North of Royal Lane), and Lenel Place and Walnut Hill Lane - Durable Specialties, Inc., lowest responsible bidder of two - Not to exceed $1,255,550.10 - Financing: Federal Highway Administration (FHWA) Emergency Relief Program Fund
Indexes: 11, 13, 6
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: June 22, 2022
COUNCIL DISTRICT(S): 6, 11, 13
DEPARTMENT: Department of Transportation
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

title
Authorize a construction contract for the Tornado-Damaged Signals Group 1 project consisting of re-construction of traffic signals located at Midway Road and Killion Drive, Preston Road (SH 289) and Preston Royal Center (North of Royal Lane), and Lenel Place and Walnut Hill Lane - Durable Specialties, Inc., lowest responsible bidder of two - Not to exceed $1,255,550.10 - Financing: Federal Highway Administration (FHWA) Emergency Relief Program Fund

body
BACKGROUND

This action will authorize a construction contract with Durable Specialties, Inc., lowest responsible bidder of two, to re-construct traffic signals located at Midway Road and Killion Drive, Preston Road (SH 289) and Preston Royal Center (North of Royal Lane), and Lenel Place and Walnut Hill Lane as part of services for the Tornado-Damaged Signals Group 1 project.
Bid specifications were developed and publicly advertised on April 27, 2022; May 4, 2022; and May 11, 2022, for competitive bids associated with the Tornado-Damaged Signals Group 1 project. Bids were opened on May 20, 2022.
The following chart illustrates Durable Specialties, Inc.'s contractual activities with the City of Dallas for the past three years:
DWU PBW PKR TRN

Current Projects 0 0 0 3
Projects Completed 0 0 0 0
Change Orders 0 0 0 0
Projects Requiring liquidated Damages 0 0 0 0
Projects Completed by Bonding Company 0 0 0 0

ESTIMATED SCHEDULE OF PROJECT

Begin construction July 2022
Complete construction March 2023

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

Fund
FY 2022
FY 2023
Future Years
Federal Highway Ad...