File #: 23-58    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 2/16/2023 In control: Department of Public Works
On agenda: 4/12/2023 Final action:
Title: Authorize a Local Project Advance Funding Agreement with the Texas Department of Transportation (CSJ No. 0918-47-234) for the replacement of the Beltline Road Bridge over Goff Branch, NBI #18-057-0-9B26-10-015 - Financing: This action has no cost consideration to the City (see Fiscal Information)
Indexes: 2
Attachments: 1. Map, 2. Resolution
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
STRATEGIC PRIORITY: Transportation & Infrastructure
AGENDA DATE: April 12, 2023
COUNCIL DISTRICT(S):|910|DEPARTMENT: Department of Public Works
EXECUTIVE: Dr. Robert Perez
______________________________________________________________________
SUBJECT

title
Authorize a Local Project Advance Funding Agreement with the Texas Department of Transportation (CSJ No. 0918-47-234) for the replacement of the Beltline Road Bridge over Goff Branch, NBI #18-057-0-9B26-10-015 - Financing: This action has no cost consideration to the City (see Fiscal Information)

body
BACKGROUND

The Beltline Road Bridge over Goff Branch is a partnership project between the City of Dallas and the Texas Department of Transportation (TxDOT) to replace the existing bridge. This bridge was included in TxDOT's currently approved off-state system federal-aid Highway Bridge Replacement and Rehabilitation Program.

This action will authorize a Local Project Advance Funding Agreement with TxDOT. The estimated total project cost is $2,021,820.00 for the preliminary engineering, construction engineering, and construction costs. The local government participation amount of $222,182.00 was waived due to the Equivalent-Match Projects. The City will commit to spending at minimum $229,000.00 plus any cost overruns on the following bridges.

-Frankford Road westbound at McKamy Branch - NBI # 18-043-09F81-00-001,
-Frankford Road eastbound at McKamy Branch - NBI #18-043-09F81-00-002 and,
-Brookview Drive at Bachman Creek - NBI # 18-057-09B79-50-001.

The appropriation of the funding for each of the three bridge projects listed will be incorporated into the Annual Bridge Maintenance Plan with an estimated timeline established by TxDOT to begin in May 2025 for the repairs to Beltline Road Bridge over Goff Branch.

ESTIMATED SCHEDULE OF PROJECT

Begin Construction May 2025
Complete Construction May 2028

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

This item has no prior action.

FISCAL INFORMATION

T...