Authorize Supplemental Agreement No. 7 to the professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide assessment, design, construction documents, and construction administration services for major maintenance and repairs to Parking Garages A and B at Dallas Love Field - Not to exceed $214,453.00, from $1,333,259.00 to $1,547,712.00 - Financing: Aviation Construction Fund
Body
BACKGROUND
Garage A was built in 1984 and currently offers parking for 3,000 vehicles. Garage B and the Pedestrian Concourse were completed in 2004. Garage B currently provides 4,000 parking spaces.
This action will authorize Supplemental Agreement No. 7 to the professional services contract with M. Arthur Gensler Jr. & Associates, Inc. to provide assessment, design, construction documents, and construction administration services for major maintenance and repairs to Parking Garages A and B at Dallas Love Field.
ESTIMATED SCHEDULE OF PROJECT
Began Design July 2014
Complete Design August 2024
Begin Construction December 2024
Complete Construction August 2025
PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)
On June 25, 2014, the City Council authorized a professional services contract with M. Arthur Gensler, Jr. & Associates, Inc. dba Gensler to perform a condition assessment of Dallas Love Field Garages A & B and the Pedestrian Concourse to identify and prioritize needed repairs and provide estimated costs of the repairs by Resolution No. 14-1012.
On May 25, 2016, the City Council authorized Supplemental Agreement No. 3 to the professional services contract with M. Arthur Gensler, Jr. & Associates, Inc. to provide design, construction documents, and construction administration services fo...