File #: 21-519    Version: 1 Name:
Type: CONSENT AGENDA Status: Approved
File created: 3/16/2021 In control: Department of Public Works
On agenda: 10/13/2021 Final action:
Title: Authorize acquisition from Sarah Barrow Reedy, Zoe Barrow Talbert, Jean T. Clarke, Frank Barrow Reedy, Julia C. Reedy and Frank Barrow Reedy, II, of approximately 416,421 square feet of land located in Kaufman County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $124,412.00 ($121,412.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund
Indexes: 200
Attachments: 1. Map, 2. Resolution, 3. Exhibit A, 4. Exhibit B
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

STRATEGIC PRIORITY:                     Mobility Solutions, Infrastructure, and Sustainability

AGENDA DATE:                     October 13, 2021

COUNCIL DISTRICT(S):                     Outside City Limits

DEPARTMENT:                     Department of Public Works

EXECUTIVE:                     Majed Al-Ghafry

______________________________________________________________________

SUBJECT

 

title

Authorize acquisition from Sarah Barrow Reedy, Zoe Barrow Talbert, Jean T. Clarke, Frank Barrow Reedy, Julia C. Reedy and Frank Barrow Reedy, II, of approximately 416,421 square feet of land located in Kaufman County for the Lake Tawakoni 144-inch Transmission Pipeline Project - Not to exceed $124,412.00 ($121,412.00, plus closing costs and title expenses not to exceed $3,000.00) - Financing: Water Construction Fund

 

body

BACKGROUND

 

This item authorizes the acquisition from Sarah Barrow Reedy, Zoe Barrow Talbert, Jean T. Clarke, Frank Barrow Reedy, Julia C. Reedy and Frank Barrow Reedy, II, of approximately 416,421 square feet of land located in Kaufman County. This property will be used for the construction of a 144-inch raw water transmission line for the Lake Tawakoni 144-inch Transmission Pipeline Project. The consideration is based on an independent appraisal. There are no relocation benefits required.

 

This acquisition is part of the right-of-way required to construct approximately 32 miles of pipeline from Lake Tawakoni to the Interim Balancing Reservoir located in Terrell, TX and then to the Eastside Water Treatment Plant located in Sunnyvale, TX. The new raw water pipeline will augment the existing 72-inch and 84-inch pipelines. The construction of this pipeline will give Dallas Water Utilities the ability to utilize the full capacity of both the Lake Tawakoni and the Lake Fork raw water supply to meet the current city needs and future water demands.

 

PRIOR ACTION/REVIEW (COUNCIL, BOARDS, COMMISSIONS)

 

This item has no prior action.

 

 

 

 

 

 

FISCAL INFORMATION

 

Fund

FY 2022

FY 2023

Future Years

Water Construction Fund

$124,412.00

$0.00

$0.00

 

OWNERS

 

Sarah Barrow Reedy

 

Zoe Barrow Talbert

 

Jean T. Clarke

 

Frank Barrow Reedy

 

Julia C. Reedy

 

Frank Barrow Reedy, II

 

MAP

 

Attached